Section 123. Hearing on application for certificate  


Latest version.
  • 1. Upon the receipt of
      an application with  respect  to  an  electric  transmission  line  that
      complies  with  section  one  hundred  twenty-two,  the commission shall
      promptly fix a date for the commencement of a public hearing thereon not
      less than sixty nor more than ninety days after such receipt. Except  as
      otherwise  provided  in section one hundred twenty-one-a of this article
      upon  the  receipt  of  an  application  with  respect  to  a  fuel  gas
      transmission line that complies with section one hundred twenty-two, the
      commission  shall  promptly  fix a date for the commencement of a public
      hearing thereon not less than twenty nor more than sixty days after such
      receipt. The testimony presented at such hearing  may  be  presented  in
      writing  or orally, provided that the commission may make rules designed
      to exclude repetitive, redundant or irrelevant testimony. The commission
      shall make a record of all testimony in all contested hearings.
        2. On an application for an amendment of a certificate, the commission
      shall hold a hearing in the same manner as  a  hearing  is  held  on  an
      application  for  a  certificate  if  the  change  in the facility to be
      authorized would result in any material increase  in  any  environmental
      impact of the facility or a substantial change in the location of all or
      a  portion of such facility other than as provided in the alternates set
      forth in the application.
        3. Unless otherwise stipulated by the applicant, a final determination
      regarding an application for a  certificate  to  construct  transmission
      facilities  for  interconnection  with a wind energy production facility
      located in the county of Lewis shall be rendered within six months  from
      the date of receipt of a compliant application.