Section 28-105.5. Application for permit  


Latest version.
  • All applications for permits shall
      be submitted on forms furnished by the  department.  Applications  shall
      include  all  information required by this code, other applicable law or
      the rules of the department. The applicant shall list  any  portions  of
      the  design that have been approved for deferred submittal in accordance
      with section 28-104.2.6. The application shall set forth  an  inspection
      program  for  the job. An application for a permit shall be submitted no
      later than 12 months after the approval  of  all  required  construction
      documents (other than those documents approved for deferred submittal).