Section 28-104.2.7. Time period for review  


Latest version.
  • Completed construction documents
      complying with the provisions of this code and other applicable laws and
      rules shall be approved  by  the  commissioner  and  written  notice  of
      approval  shall  be  given  the  applicant promptly and no later than 40
      calendar days after the submission of a complete application.
        Exceptions:
        1. On or before the fortieth day, the commissioner may, for good cause
      shown and upon notification to the applicant, extend such  time  for  an
      additional 20 calendar days.
        2.  Such  time  period  for  review  shall commence in accordance with
      article 107 for single room occupancy multiple dwellings.