Section 28-104.2.6. Deferred submittal  


Latest version.
  • With  the  prior  approval  of  the
      department, the applicant may defer submittal of portions of the  design
      until  a  specified  period  of time after the issuance of a permit. The
      applicant shall  list  the  deferred  submittal  items  on  the  initial
      application  for  construction document approval. The deferred submittal
      items shall not  be  constructed  or  installed  until  the  design  and
      submittal documents for the item have been approved by the department.