Section 121. Certificate of environmental compatibility and public need  


Latest version.
  • 1.
      No person shall, after July first, nineteen  hundred  seventy,  commence
      the  preparation  of  the  site  for the construction of a major utility
      transmission facility in the  state  without  having  first  obtained  a
      certificate of environmental compatibility and public need (hereafter in
      this  article  called  a  "certificate")  issued  with  respect  to such
      facility by the  commission.  The  replacement  of  existing  with  like
      facilities,  as  determined  by the commission, shall not constitute the
      construction of a major utility transmission facility. Any facility with
      respect to which a certificate is required shall  thereafter  be  built,
      maintained  and  operated  in  conformity  with such certificate and any
      terms, limitations or conditions contained therein.   A certificate  may
      only be issued pursuant to this article.
        2.  A  certificate  may be transferred, subject to the approval of the
      commission, to a person who agrees to comply with the terms, limitations
      and conditions contained therein.
        3. A certificate issued hereunder may be amended as herein provided.
        4. This article shall not apply  to  any  major  utility  transmission
      facility:
        a.  For  which,  on  or before July first, nineteen hundred seventy an
      application has been made for a license,  permit,  consent  or  approval
      from any federal, state or local commission, agency, board or regulatory
      body,   in   which   application  the  location  of  the  major  utility
      transmission facility has been designated by the applicant;
        b. The construction of which has been approved by  a  municipality  or
      public  benefit  corporation  which  has sold bonds or bond anticipation
      notes on or before July first, nineteen hundred seventy, the proceeds or
      part of the proceeds of which are to be used in payment therefor; or
        c. Over which any agency or department of the federal  government  has
      exclusive  jurisdiction, or has jurisdiction concurrent with that of the
      state  and  has  exercised  such  jurisdiction,  to  the  exclusion   of
      regulation of the facility by the state.
        5.  Any  person  intending  to  construct a major utility transmission
      facility excluded from this article pursuant  to  subdivision  four  may
      elect to waive such exclusion by delivering notice of such waiver to the
      commission.  This  article  shall thereafter apply to each major utility
      transmission facility identified in such notice from  the  date  of  its
      receipt by the commission.