Section 2307. Additional prerequisites to the provision of financial assistance  


Latest version.
  • Prior to providing any financial assistance of more than one  hundred thousand dollars to any project, the authority must comply  with
      the following prerequisites:
        1.  The  authority  must adopt a resolution describing the project and
      the financial  assistance  that  the  authority  is  contemplating  with
      respect  to  such  project. Such assistance shall be consistent with the
      uniform  tax  exemption  policy  adopted  by  the  agency  pursuant   to
      subdivision one of section twenty-three hundred fifteen of this chapter,
      unless the agency has followed procedures for deviation from such policy
      specified in subdivision two of such section.
        2.  The  authority  must  hold  a  public  hearing with respect to the
      project and the proposed financial assistance being contemplated by  the
      authority.  At said public hearing, interested parties shall be provided
      reasonable opportunity, both orally and in  writing,  to  present  their
      views with respect to the project.
        3.  The authority must give at least ten days published notice of said
      public hearing and shall, at the  same  time,  provide  notice  of  such
      hearing   to   the   chief   executive  officer  of  each  affected  tax
      jurisidiction within which the project is located. The notice of hearing
      must state the time  and  place  of  the  hearing,  contain  a  general,
      functional description of the project, describe the prospective location
      of  the  project, identify the initial owner, operator or manager of the
      project and generally describe the financial assistance contemplated  by
      the authority with respect to the project.