Section 1269-C. Metropolitan transportation authority capital program review board; additional powers and duties  


Latest version.
  • a. The metropolitan transportation  authority  capital  program  review  board,  consisting  of  voting  and
      non-voting  members  shall  (1)  monitor  the  progress  of  the capital
      elements described in each plan approved as provided in  section  twelve
      hundred  sixty-nine-b  of  this  title;  (2)  monitor  the  expenditures
      incurred and to be incurred for each such element; (3) identify  capital
      elements  not  progressing  on  schedule;  (4)  ascertain responsibility
      therefor; and (5) recommend those actions  required  or  appropriate  to
      accelerate  their  implementation.  The authority shall consult with the
      board upon its request and provide it with access to the records of  the
      authority relating to such capital elements.
        b.  The  authority  shall submit to the review board within sixty days
      after the end of each calendar year (1) the actual commitments  for  the
      capital  plan  for  the  previous  calendar  year  compared  to  planned
      commitments by capital element; (2) expenditures by funding  source  for
      each capital element in the previous calendar year; and (3) the proposed
      funding  of  capital elements in a plan for the current calendar year by
      funding source. Such submission shall be certified by  the  chairman  of
      the  authority  and  shall  be  entered into the permanent record of the
      minutes of the review board.