Section 11-102. Liability of utilities for compensation for damages caused by interfering with, or delaying the progress of work under state public construction contracts  


Latest version.
  • 1. No utility shall interfere with, or delay the  progress of work under any contract with the state  department,  agency,
      division  or  board, for the construction, reconstruction or improvement
      of any highway, street, road, railroad grade crossing,  bridge,  tunnel,
      underpass,  overpass  or other state contract work, by failing to remove
      or relocate its poles, wires,  cables,  conduits,  pipes  or  any  other
      facilities  or  structures  within  the  time  schedule  therefor  by an
      agreement or under the terms of an  agreement  between  the  department,
      agency,  division  or  board  and the utility, or if no time is fixed by
      such an agreement or under the terms of such an  agreement,  within  the
      time  fixed  by  the  department,  agency,  division or board, by notice
      served upon such utility by such state department, agency,  division  or
      board.
        2.   If  such  notice  is  utilized,  it  shall  describe  the  public
      improvement  and  the  geographical  location  thereof,  the   date   of
      commencement  and  the  date  of completion, if any, provided for by the
      contract, the contractor's name and address, the manner in which and the
      extent to which the facilities and structures of the utility obstruct or
      prevent  the  contractor  from  progressing  or  performing   the   work
      comprehended by the contract, and shall fix the date or time within such
      utility  is required to remove or relocate its facilities or structures,
      specifying the same, in order to provide the contractor  with  the  site
      when  required  by the contractor for progressing or performing the work
      pursuant to such state contract. Such notice shall  be  in  writing  and
      shall be served upon such utility either personally or by certified mail
      at  its  principal  office  or place of business in the county where the
      work under such contract is to be performed, or, if  there  be  no  such
      principal  office  or  place  of business in such county, at the nearest
      principal office or place of business of such utility, outside  of  such
      county.  In  the  event  the  utility  to  whom the aforesaid notice was
      directed is for any reason unable,  within  the  prescribed  period,  to
      remove  or  relocate  said  facilities  or  structures  specified in the
      notice, said utility shall immediately advise said  department,  agency,
      division or board and the contractor, in writing, of such inability, and
      in the same communication so advise said department, agency, division or
      board,  and  the contractor of the approximate date that such removal or
      relocation of facilities or structures  could  be  effected;  and  shall
      further  state  the basis for the inability of said utility to remove or
      relocate said facilities or structures within the time specified by  the
      notice served thereon by said department, agency, division or board. The
      department,  agency,  division or board, after examining and considering
      the utility's basis for  establishing  a  different  schedule  for  such
      removal or relocation, shall, if such basis is reasonable, establish and
      notify  the utility of a revised schedule for completing such removal or
      relocation.
        3. In cases  where  the  utility  has  been  reimbursed  for  removal,
      relocation,   replacement  or  reconstruction  pursuant  to  subdivision
      twenty-four-b of section ten of the highway law, a  utility  failing  to
      complete  the  removal  or  relocation  of such structures or facilities
      within a period of thirty days beyond the time  fixed  therefor  by  the
      latest  time schedule established in accordance with this section, shall
      be liable and responsible to any such contractor for any damages, direct
      or consequential,  sustained  by  any  such  contractor  as  the  result
      thereof,  in  an  action  to  be brought by such contractor against such
      utility in a court of competent jurisdiction within two years  from  the
      time  fixed  for  the  removal  or  relocation  of  such  structures  or
    
      facilities. If an action is commenced against a utility,  as  heretofore
      provided,  said  utility  may interpose in its answer in such action any
      defense available under the provisions of the  civil  practice  law  and
      rules.  The  unreasonableness  of the time schedule imposed by the state
      department, agency, division or board shall be an  absolute  defense  by
      the  utility  to  any  such  action  by  the contractor. If, in any such
      action, the utility is found to owe nothing to the contractor, or if  an
      offer  of settlement is made by the utility which is not accepted by the
      contractor and the resulting verdict against the utility  is  less  than
      the offer of settlement, then in either such event the total cost of the
      utility  of  litigation,  including reasonable attorney's fees, shall be
      paid to the utility by the contractor.