Section 756-A. Obligations  


Latest version.
  • It is the policy and purpose of this article to
      expedite payment of all monies owed to  those  who  perform  contracting
      services   pursuant  to  construction  contracts.  Except  as  otherwise
      provided in this article, the terms and  conditions  of  a  construction
      contract  shall  supersede the provisions of this article and govern the
      conduct of the parties thereto.
        1. Billing cycle. The parties  to  a  construction  contract  may,  by
      mutual  agreement,  establish  a  billing  cycle  for  the submission of
      invoices  requesting  payment  for  work   performed   pursuant   to   a
      construction  contract. In the absence of an agreement by the parties as
      to the billing cycle, the billing cycle  shall  be  the  calendar  month
      within which the work is performed.
        2.  Invoices.  (a) A contractor shall be entitled to invoice the owner
      for interim payments at the end of the billing cycle. A contractor shall
      be entitled to submit a final invoice  for  payment  in  full  upon  the
      performance of all the contractor's obligation under the contract.
        (i)  Upon  delivery  of  an  invoice  and  all  contractually required
      documentation, an owner shall approve or disapprove all or a portion  of
      such  invoice  within  twelve  business days. Owner approval of invoices
      shall not be unreasonably withheld nor shall  an  owner,  in  bad  faith
      disapprove  all  or  a  portion  of  an invoice. If an owner declines to
      approve an invoice or a portion thereof, it must  prepare  and  issue  a
      written  statement  describing  those  items in the invoice that are not
      approved. An owner may decline to approve an invoice or  portion  of  an
      invoice for:
        (1) Unsatisfactory or disputed job progress;
        (2) Defective construction work or material not remedied;
        (3) Disputed work materials;
        (4)   Failure   to  comply  with  other  material  provisions  of  the
      construction contract;
        (5) Failure of the  contractor  to  make  timely  payments  for  labor
      including  collectively  bargained fringe benefit contributions, payroll
      taxes and insurance, equipment and materials, damage to  the  owner,  or
      reasonable  evidence  that the construction contract cannot be completed
      for the unpaid balance of the construction contract sum; or
        (6) Failure of the owner's architect to certify payment for any or all
      of the reasons set forth in this section so  long  as  the  reasons  are
      included in the owner's written statement of disapproval.
        (ii)  Upon  delivery  of  an  invoice  and  all contractually required
      documentation, a contractor or subcontractor shall approve or disapprove
      all or a portion of such invoice within twelve business days. Contractor
      and  subcontractor  approval  of  invoices  shall  not  be  unreasonably
      withheld  nor  shall  a  contractor  or  subcontractor,  in  bad  faith,
      disapprove all or a portion of an invoice. Nothing in this section shall
      prohibit the contractor or subcontractor, at the time of application  to
      the  owner or contractor, from withholding such application to the owner
      or contractor for payment to the subcontractor or material supplier for:
        (1) Unsatisfactory or disputed job progress;
        (2) Defective construction work or material not remedied;
        (3) Disputed work;
        (4)  Failure  to  comply  with  other  material  provisions   of   the
      construction contract; or
        (5)  Failure  of  the  subcontractor to make timely payments for labor
      including collectively bargained fringe benefit  contributions;  payroll
      taxes  and  insurance,  equipment and materials, damage to contractor or
      another subcontractor or material supplier, or reasonable evidence  that
      the  subcontract  cannot  be  completed  for  the  unpaid balance of the
      subcontract sum.
    
        (b) Nothing in this subdivision shall authorize the withholding of  an
      application   to   the   owner  or  contractor  for  the  payment  to  a
      subcontractor or material supplier when due to a delay in  job  progress
      by  the  owner, contractor or another subcontractor or material supplier
      other  than  the  applicant  or  applicant's  subcontractor  or material
      supplier.
        3. Payment. (a) The owner's payment  of  a  contractor's  interim  and
      final  invoices shall be made on the basis of a duly approved invoice of
      work performed and the material supplied during the billing cycle.
        (i) Unless the provisions of this article provide otherwise, the owner
      shall pay the contractor strictly in accordance with the  terms  of  the
      construction contract.
        (ii)  Payment  of  an  interim  or final invoice shall be due from the
      owner not later than thirty days after approval of the invoice.
        (iii) If payment by the owner  is  contingent  upon  lender  approval,
      payment of a contractor's interim or final invoice or the amount of loan
      proceeds disbursed by the lender for payment of the contractor's interim
      or final invoice shall be due from the owner seven days after receipt by
      the  owner  of  good  funds except where the provisions of section seven
      hundred fifty-six-d of this article applies.
        (iv) An owner may withhold from an interim payment only an amount that
      is sufficient to pay the costs and expenses the owner reasonably expects
      to incur in order to cure the defect or correct any items set  forth  in
      writing pursuant to subparagraph (i) of paragraph (a) of subdivision two
      of  this  section,  or  in the alternative, to withhold an amount not to
      exceed the line item amount appearing in the agreed schedule  of  values
      together  with  any  change  orders, additions and/or deletions, if such
      schedule has been previously submitted, and/or an amount  sufficient  to
      cover  liquidated  damages  as established in an agreed upon schedule in
      the construction contract.
        (b) The contractor or  subcontractor's  payment  of  subcontractor  or
      material  supplier's interim or final invoice shall be made on the basis
      of a duly approved invoice of the work performed and materials  supplied
      during the billing cycle.
        (i)  Unless  the  provisions  of  this  article provide otherwise, the
      contractor or subcontractor shall  pay  the  subcontractor  strictly  in
      accordance with the terms of the construction contract. Performance by a
      subcontractor  in  accordance  with the provisions of its contract shall
      entitle  it  to  payment  from  the  party  with  which  it   contracts.
      Notwithstanding   this   article,  where  a  contractor  enters  into  a
      construction contract with a subcontractor  as  agent  for  a  disclosed
      owner,  the  payment  obligation  shall flow directly from the disclosed
      owner as principal to the subcontractor and through the agent.
        (ii) When  a  subcontractor  has  performed  in  accordance  with  the
      provisions of its construction contract, the contractor shall pay to the
      subcontractor,   and  each  subcontractor  shall  in  turn  pay  to  its
      subcontractors, the full or proportionate amount of funds received  from
      the  owner  for each subcontractor's work and materials based on work or
      services provided under the  construction  contract,  seven  days  after
      receipt  of  good  funds for each interim or final payment, provided all
      contractually required documentation and waivers are received.
        (iii) A contractor or subcontractor may withhold amounts received from
      an owner in connection with an interim payment due to a subcontractor or
      material supplier only such sums that are sufficient to pay  the  direct
      expenses  as  are reasonable to correct deficiencies identified pursuant
      to subparagraph (ii)  of  paragraph  (a)  of  subdivision  two  of  this
      section,  or in the alternative, to withhold an amount not to exceed the
      line item amount appearing in the agreed schedule  of  values,  together
    
      with any change order, additions or deletions, if such schedule has been
      previously submitted.
        (iv)  If a contractor, after submitting an invoice to an owner under a
      construction contract, but before making a payment to a subcontractor or
      material  supplier  for  the  subcontractor's  or  material   supplier's
      performance  covered by such invoice, discovers that all or a portion of
      the payment otherwise due to the subcontractor or material  supplier  is
      subject  to  withholding  from the subcontractor or material supplier in
      accordance with the construction contract and the conditions  set  forth
      in  subparagraph  (ii)  of  paragraph  (a)  of  subdivision  two of this
      section, then the contractor shall:
        (1) As soon as practicable upon ascertaining the cause giving rise  to
      a withholding, but prior to the due date for a subcontractor or material
      supplier  payment, furnish to the subcontractor or material supplier and
      the owner  written  notice  of  withholding  specifying  conditions  for
      withholding payment and identifying the amount to be withheld;
        (2)  Reduce the subcontractor's or material supplier's interim payment
      by an amount not to  exceed  the  amount  specified  in  the  notice  of
      withholding; and
        (3) Pay the subcontractor or material supplier amounts withheld within
      seven  days after correction of the identified subcontractor or material
      supplier  performance   deficiency   and   receipt   of   all   required
      documentation  and  waivers,  unless the funds therefor must be obtained
      from the owner's  next  interim  payment  due  to  a  reduction  in  the
      contractor's  billing  directly  resulting  from  the subcontractor's or
      material supplier's performance deficiency identified in the  notice  of
      withholding.
        (c)  A  written notice of any withholding under this subdivision shall
      be issued to a subcontractor or material supplier specifying:
        (i) The amount to be withheld;
        (ii) The specific causes  for  withholding  under  the  terms  of  the
      construction contract and pursuant to this subdivision;
        (iii)  The remedial actions necessary to be taken by the subcontractor
      or material supplier  in  order  to  receive  payments  of  the  amounts
      withheld; and
        (iv) The documentation and waivers required.
        4.   Notice.  A  contractor  or  subcontractor  shall  disclose  to  a
      subcontractor, at the time the construction subcontract is entered into,
      the due date for receipt of payments to the contractor or  subcontractor
      from  the owner or the contractor as the case may be. If a contractor or
      subcontractor  fails  to  accurately  disclose  the  due   date   to   a
      subcontractor, the contractor or subcontractor shall be obligated to pay
      the  subcontractor  as though the due dates established in paragraph (a)
      of subdivision three of this section were met by the owner. In addition,
      upon written request of a subcontractor, the owner shall provide  notice
      to  such  subcontractor  within five days of making any interim or final
      payment to the contractor. The subcontractor's request shall  remain  in
      effect for the duration of the subcontractor's work on the project.