Section 28-217.3. Compliance monitoring  


Latest version.
  • The  SCO  shall  monitor  the
      operations  related  to  the  circumstances  and  conditions  that   the
      commissioner has identified pursuant to section 28-217.2 until the areas
      of  concern  set  forth  by  the  commissioner  have  been  addressed as
      determined by the commissioner, but in  no  case  shall  any  monitoring
      period  exceed  ninety  days.  For  such purpose, the SCO and his or her
      employees shall be  designated  as  authorized  representatives  of  the
      commissioner  with  authority pursuant to section 28-103.13 of this code
      to enter upon and examine and inspect at all reasonable times any  site,
      building  or  structure. In the event that the conditions set-out in the
      commissioner's determination, pursuant to section 28-217.2, to require a
      SCO have not been satisfied within the prescribed monitoring period, the
      commissioner may appoint another SCO, who shall be a different SCO  than
      the  initial  SCO, to monitor operations for an additional period not to
      exceed ninety days.
        * NB There are 2 § 28-217.3's