Section 28-116.2.4.1. Final inspection prior to certificate of occupancy  


Latest version.
  • In
      all cases where the permitted work requires the issuance  of  a  new  or
      amended   certificate  of  occupancy,  the  final  inspection  shall  be
      performed by the department in the presence of the, permit  holder,  the
      registered  design  professional  of  record  or  the  superintendent of
      construction.  Such  inspection  shall  be  performed  after  all   work
      authorized  by  the building permit is completed and before the issuance
      of the certificate  of  occupancy.  All  failures  to  comply  with  the
      provisions  of  this  code  or  approved construction documents shall be
      noted and the owner promptly notified thereof in  writing.  All  defects
      noted  in  such  inspection  shall  be  corrected. Reports of such final
      inspections shall be maintained by the department. The final  inspection
      report  shall  confirm  that defects noted have been corrected, that the
      work  is  in  substantial  compliance  with  the  approved  construction
      documents  and  with  this code and with other applicable laws and rules
      and that all required inspections were performed.