Section 28-116.2.3. Special inspections and other inspections required during the progress of work  


Latest version.
  • After  the  issuance of a work permit, special  inspections and other inspections required  by  this  code  to  be  made
      during  the  progress of the work shall be made at such times or at such
      stages of the work and in such manner as shall be provided by this  code
      or  as  otherwise  required  by the commissioner. The permit application
      shall set forth an inspection program for the job. Such inspections  may
      be  made  by  approved agencies or by the department as provided in this
      code or in the rules of the department.  Special  inspections  shall  be
      performed  only  by  individuals  who are special inspectors. The permit
      holder shall notify the relevant special inspectors in writing at  least
      72  hours  prior  to  the  commencement  of  any  work requiring special
      inspection. The commissioner may accept inspection and test reports from
      approved agencies and  special  inspectors  and  the  work  may,  unless
      otherwise  specifically  provided  by code provisions or directed by the
      commissioner, proceed without any verifying inspection or  test  by  the
      department.  The  names and business addresses of special inspectors and
      approved agencies shall be set forth in the work permit application. All
      inspection reports shall be in writing  and  signed  by  the  person  or
      entity  performing  the inspection. A record of all inspections shall be
      kept by the person  performing  the  inspection.  The  commissioner  may
      require  inspection  reports to be filed with the department. Records of
      inspections made by approved agencies and special  inspectors  shall  be
      maintained  by  such persons for a period of six years after sign-off of
      the job or for such other period of time as the commissioner may require
      and shall be made available to the department upon request.