Section 28-104.2.9. Resubmission  


Latest version.
  • Whenever  an application has been rejected
      and is thereafter revised and resubmitted to meet the stated grounds  of
      rejection,  the  revised application and construction documents shall be
      approved if they meet the stated  grounds  of  rejection  and  otherwise
      comply  with  the  provisions of this code and other applicable laws and
      rules or shall be rejected if they fail to meet the  stated  grounds  of
      rejection  or otherwise fail to so comply. Written notice of approval or
      written notice of rejection, stating the grounds of rejection, shall  be
      given  the  applicant promptly and not later than 20 calendar days after
      the resubmission of such documents.