Section 28-104.2.5. Phased or partial approval  


Latest version.
  • In the case of construction
      documents for the construction of new buildings  or  the  alteration  of
      buildings,  the  commissioner may grant partial approval of construction
      documents for the issuance of foundation and  earthwork  permits  before
      the  construction  documents  for  the entire building or structure have
      been submitted. The  approval  of  such  partial  applications  will  be
      subject  to  the submittal and approval of construction documents, filed
      together or separately, comprising:
        1. The  lot  diagram  showing  the  exact  location  of  the  lot  and
      dimensions to the nearest corner;
        2.  A complete zoning analysis showing compliance of the proposed work
      with the zoning resolution;
        3. The foundation plans, as provided for in this code; and
        4. The floor and roof plans showing compliance with exit requirements,
      as provided for in this code.
        The issuance of such foundation and earthwork  permit  is  subject  to
      submission  of required submittal documents. The owner and the holder of
      such foundation and earthwork permit shall proceed  at  their  own  risk
      with  the construction operation and without assurance that a permit for
      the entire structure will be granted.