Section 27-690. Use of existing piles at demolished structures  


Latest version.
  • Piles left in
      place  where  a  structure has been demolished shall not be used for the
      support of new construction unless satisfactory evidence, including load
      or hammer testing of representative piles, can  be  produced  indicating
      the  capacity,  length,  and  driving  conditions of the piles. The load
      bearing value for such existing piles shall be the least of  the  values
      indicated  by: (1) the load or hammer test, (2) the capacity of the pile
      as a structural member, and (3) the allowable bearing  pressure  on  the
      soil  underlying the pile tips, all in accordance with the provisions of
      article eight of this subchapter.