Section 27-664. Test pits  


Latest version.
  • (a) Test pits may be substituted for boring on a
      one-for-one basis. All applicable requirements as to depth,  numbers  of
      samples,  data  to  be  reported,  and  disposition  of samples shall be
      observed, except that the use of  sample  spoon,  recording  of  driving
      resistance,  and  recovery  of  rock  cores  is not required in test pit
      investigations, and except  as  provided  in  subdivision  (b)  of  this
      section.
        (b)  Test  pits for buildings not more than one story in height or for
      one or two-family residences not more than two stories  in  height  need
      only  extend  four feet below the deepest part of the excavation for the
      construction of footings, or a minimum  of  four  feet  when  foundation
      elements  rest on grade pursuant to paragraph four of subdivision (a) of
      section 27-658 of article one of this  subchapter,  provided  that  such
      structures  are  supported by footings bearing on nominally satisfactory
      bearing materials of class 9-65 (except soft clay) soil or better.