Section 27-628. Erection


Latest version.
  • (a) Bracing. All framework shall be carried up true
      and  plumb.  Temporary  bracing  shall  be provided to support all loads
      imposed upon the framework during construction that  are  in  excess  of
      those for which the framework was designed.
        (b)  Temporary  connections. As erection progresses, the work shall be
      securely bolted, or welded, to resist all dead loads, wind, and erection
      stresses.
        (c)  Alignment.  The  structure  shall  be  properly  aligned   before
      riveting, permanent bolting, or welding is performed.