  • (a)  The  commissioner  shall act within a reasonable time not to exceed
      sixty days on an application for a tunneling permit,  for  an  operating
      certificate,  or  for  a  renewal of an operating certificate, and shall
      notify the applicant in writing of his or her approval or disapproval of
      the application.
        (b) If an application is disapproved, the commissioner shall set forth
      his or her  objections  in  the  notice  of  disapproval  or  notice  of
      violation.
        (c)  Within sixty days after service on the applicant of the notice of
      disapproval, exclusive of the day of service, the applicant may  request
      the  commissioner  to reconsider the application by answering in writing
      the commissioner's objection to the application.
        (d) The commissioner shall consider the applicant's answer to  his  or
      her  objections,  and  shall  notify  the  applicant in writing within a
      reasonable time, not to exceed sixty days, of his  or  her  approval  or
      denial  of the application. Failure to answer or request an extension of
      time within sixty days after service of the notice of disapproval  or  a
      notice of violation shall be deemed a denial of the application.
        (e)  The  commissioner  may grant a temporary operating certificate or
      tunneling permit for a period not to exceed sixty days upon  receipt  of
      an  application  for the granting or renewal of an operating certificate
      and  may,  at  his  or  her  discretion,  renew  a  temporary  operating
      certificate  or  tunneling permit for an additional period not to exceed
      sixty days.