Section 11-254. Extension of time for completion  


Latest version.
  • Where an applicant has
      received a certificate of eligibility but has not completed or will  not
      be  able  to  complete  the  construction  or reconstruction work within
      thirty-six  months,  the  board  shall,  upon  application,  extend   to
      forty-eight  months,  from the time of issuance of such certificate, the
      time for completion of the construction or reconstruction work; provided
      the applicant has completed not less than  two-thirds  of  the  work  as
      specified  in  the certified plans previously filed with the application
      at the time of such application for extension.